McCollum – Client Meeting – 2026.03.26
Steel Detailing And Staircase
Jeff reviewed and signed off on original steel design intent — renderings were a key factor in approval
Keith has questions for Monday regarding the door at the staircase level
Peter to produce stair flange and steel detail — has material in hand, estimated one week turnaround
Steel sign-off frees the masonry crew to move from the hallway to the staircase efficiently
Fireplace Doors
Peter provided pricing for fireplace doors — Brett to forward to Jeff
Jeff is expecting this as an add and has been advised accordingly
Fireplace steel skeleton not yet started — team pivoted focus to hall wall and staircase first
Shower Glass Channels
Primary Bath (Upstairs)
Recessed channels required — must be addressed after dry-in using Schluter fabric before tile on curbs and vertical surfaces
Floor tile can proceed before channels are in place; curb and vertical tile cannot
Brett to follow up with Fernando on site visit and channel detail confirmation
Finish preference: brushed nickel or anodized aluminum — nothing shiny; match hardware finish if possible
Stock finish acceptable given minimal visibility through glass
Lower Bath (Bypass)
Surface-mounted glass channel package confirmed — no recessed condition required
Structural Beams And Columns
Structural engineer confirmed beams can be textured in place — limit sanding to no more than 1/16 inch; chisel texture is approved
Painter believes Douglas fir beams can potentially be stained to approximate white oak tone but noted it would not be easy and requires samples and process development
Consensus: in-place staining of fir is risky — stain depth and color consistency are difficult to achieve and could impact schedule
Preferred path remains box beam wrap in matching veneer — consistent with columns, headers, hallway, and mudroom
Beam wrap samples arriving — half received, remainder expected by Friday
Team to review beam samples on Wednesday before committing to a path
Previous sample rejected due to poor color and excessive chisel/distressing — new samples expected to be closer to target
Solarium Structure
Solarium framing to be sanded smooth and painted to match the window package — black bronze to blend with existing window frames
Painter to reference existing windows for color match
Ellis to confirm and select specific paint color
Tile And Drains
Drains arriving Friday — tile crew to begin packing shower pans upon receipt
Tile installation has not yet begun — timing was optimistic in prior meeting
Overall project schedule not currently impacted by drain delay
Plan remains to install bathroom cabinetry before floor tile — no reason to change this sequence at this time
Drywall And Texture
Currently in second coat of mud — corners being built, sanding in preparation for texture
Significant texture progress expected by Wednesday
Wood Floors
Floors are in Haley — installation timeline being coordinated around labor availability, drywall/paint sequence, and masonry sequence
Stone must dry before installation can proceed
Stone Masonry
Masonry has not started in the hallway or living room — was held pending steel sign-off
Steel approval now allows masonry crew to return and work continuously from hallway through staircase
Cabinet Finish Sample
Cabinet sample needed by Wednesday for painter to develop finish match
Ellis to bring cabinet sample to Wednesday meeting — Reagan to set it out in advance
Plan to cut sample in half so Ellis retains a control piece
Door and trim color sample currently in progress — to be reviewed Wednesday
Mesh For Cabinetry And Fireplace Door
Mesh sample used in fireplace door prototype is at the office — no product identification or source noted on sample
Same mesh to be used in laundry room cabinetry and fireplace door
Reagan confirmed mesh is in hand — Peter can borrow it if needed to identify source
Brett to track down mesh product details
Stone Slabs
Ellis anticipates slab selection on Monday from local LA slab yards, including one in Petaluma
Brett to confirm fabricator's process for owner-provided slabs and coordinate payment and purchase protocol
Brett to provide delivery address and fabricator contact to Ellis ahead of Monday
Brett available Monday to act as intermediary if slab purchase needs to move quickly
Some slab yards will not sell directly to homeowners — fabricator purchase may be required
Precedent: Brunatini project used owner-provided slabs with Classic as fabricator — similar arrangement may apply here
Action Items Summary
Brett — follow up with Fernando on shower channel recessed detail (upstairs)
Brett — send fireplace door pricing to Jeff
Brett — confirm fabricator process and contact for slab purchase; provide delivery address to Ellis
Brett — have painter reference window package for solarium paint color match
Brett — get beam wrap samples ready for Wednesday review
Reagan — set out cabinet sample for Wednesday morning meeting
Reagan — locate mesh product source information; make available for Peter if needed
Ellis — bring cabinet sample to Wednesday meeting; cut in half to retain control piece
Ellis — confirm solarium paint color selection
Ellis — pursue slab selection Monday; coordinate with Brett on purchase logistics